Thursday 20th October 2016

img_4229 img_4225 img_4218 img_4226 img_4220 img_4214 img_4228 img_4212

A lot has happened in just over a week.  Most of the roofing sections for the main building have been lifted into place by the crane.  Meanwhile, the walls for the changing rooms are well underway in the PE block.  Excellent progress!  Also included in these photographs are the views from the Head Teacher’s office window.  What a change since March when the playing fields became a building site.  This was my final view from my office this afternoon before retirement.  Hugh McCulloch takes over as Head Teacher next week.  He has been heavily involved in the project and will see it through – including keeping this blog going.  I look forward to returning for the handover of the building in October 2016 and seeing the dreams of my 13 years at Elgin High School become a reality.  We didn’t make the original target of summer 2015, but it has been great working with folk from Balfour Beatty, Hubco and Moray Council and I am delighted that the pupils and staff of EHS will soon be able to enjoy modern, first class facilities that they so richly deserve.  Thank you!

Andy Simpson

Week beginning 10th October 2016

img_4197 161003-balfourbeatty-fb-013 img_4199 img_4164 img_4191 img_4196 img_4168 img_4169 img_4188 img_4171

161003-balfourbeatty-fb-053

Amazing aerial photographs show the new build against a background of much of the EHS catchment area. The roof on the PE block is finished and the roofing materials for the main block were being unloaded this afternoon with the return of the huge crane. Meanwhile the concrete for the PE floor has been laid and is starting to be poured for the main block. Very good progress!  Very much enjoyed my brief visit to the site on Friday – good to be able to get onto the first floor and get a real sense of the layout.  Thank you!  An excellent way to mark my retirement.

Monday 12th September 2016

IMG_4102 IMG_4098 IMG_4103 160901-DJI_0022-web 160901-DJI_0012-web 160901-DJI_0037-web IMG_4094 IMG_4099 160901-DJI_0029-web

Latest photographs include a selection taken by a drone flying over the site last week.  However, even since then the buildings have changed.  The roof is now on the PE block.  Everyone was fascinated to watch the giant crane lift the sections along the length of the building.  Meanwhile the frame for the main building continues to grow and cannot be far from completion.  The school website – www.elginhigh.moray.sch.uk – has a link to a time lapse film of the first months of construction.

Week Beginning 5th September 2016

IMG_4087 IMG_4086 IMG_3920 IMG_4083 IMG_4078 IMG_4081 IMG_4080 IMG_3925 IMG_4077

Last week’s visitors from Zambia thoroughly enjoyed their stay in Elgin.  The had the opportunity to inspect the construction site and were very impressed.  This week the work continues to advance quickly.  The frame of the main building is almost complete.  The arrival of the massive crane will see the roof sections for the PE block moved into place.  Meanwhile there have been useful meetings finalising details of some interior areas.

Monday 22nd August 2016

IMG_3766 IMG_3763 IMG_3767 IMG_3772 IMG_3770

160809-BalfourBeatty-print-008 160809-BalfourBeatty-print-012

What a change over  a few days.  The aerial pictures were taken on Wednesday 10th August.  Less than two weeks later the frame for the main building is well under way and growing fast every day.  The PE block is ready for the roof to be added later this week.  A group of Zambians arrive tomorrow.  We are looking forward to give them a tour of the construction site.

Monday 15th August 2016

DSC_0680 DSC_0679

Today the new session started for staff and tomorrow the pupils return.  It will be great to watch the reaction of the young people as they see the change in the new build over the summer.  A second crane arrived today and it was amazing to see how quickly new sections of the frame were constructed.  A quick meeting with Balfour Beatty staff has helped prepare plans for further involvement of pupils and staff with educational projects and visits.

Tuesday 9th August 2016

IMG_3758 IMG_3759

SQA results day today.  There was much to celebrate amongst EHS pupils with some excellent passes at all levels of SQA courses.  Well done to everyone.  Meanwhile the work on the new building continues.  The lift shafts are now in place.  This has been quickly followed by work on the steel frame.  Quite a change in the view from the library window!

Thursday 28th July

IMG_3738 IMG_3746 IMG_3736 IMG_3745 IMG_3743 IMG_3735

Three weeks is a long time on a construction site!  Since the start of the holidays there have been big changes – particularly with the steel framework for the PE department now in place.  Concrete was being poured for the foundations of the main block with signs that there will soon be changes to be seen there with the building of the lift shafts.  Good to see several members of the local community looking at the site with high levels of interest.