No pictures this week, but more encouraging news. Arrangements are being made to divert the gas pipes to allow EHS and Greenwards Primary to keep functioning while construction work is taking place. There was also a meeting with Balfour Beatty to look at start dates – still scheduled for site preparation in March and construction work proper in April. We had sight of plans showing the construction areas for the different phases of the project between March 2015 and May 2017. These will allow the school to manage the safety of the pupils while work is going on. The other main discussion this week was what equipment and resources we will take from the old building to the new. This is not an easy question when you think of all that a school building contains. The latest parent newsletter was issued on Friday – the front cover included the architect’s pictures of what the building will be like.