Update – 11 October

Following a story in the local press, The Moray Council has issued the following statement to keep pupils, parents, staff and the local community up to date with developments:

It became apparent at an early stage that a start date of March 2014 was highly ambitious and while everyone involved is keen to see construction begin as soon as possible, they are even more keen that the project provides a new secondary school that is fit for purpose and will serve the local community well for years to come.

“Issues have emerged in relation to ground conditions on part of the site which require to be investigated further.

“As a result, possible courses of action include repositioning the new building within the overall site and options for that are currently being examined in detail.

“The cost implications of these options cannot be accurately quantified at this stage but all parties are continuing to work closely in an endeavour to keep the project within budget.

“What can be said with certainty is that although the project is currently showing an overspend on the original budget figure, it is nowhere near £4million.

“The project and the council continue to be fully supported by the Scottish Futures Trust, and the funding for the project is thus secure.”

Leave a Reply

Your email address will not be published. Required fields are marked *