Project Update – March 2017

The construction of our new school continues and staff have been visiting the site with interest.

Kier Construction, our lead contractor, are now in week number 53 of a 108 week build programme and are still on programme to hand over in March 2018.  They have commenced internal fit out on all floors—with erection of partitions & installation of mechanical & electrical services.  The envelope is progressing well and we expect the build will be wind and water tight by early April.